TRANSFORMER SUBSTATIONS AND POWER GRIDS

  • The execution of 6kV and respectively 20kV underground power lines for the supply of auxiliary services from the 400/220/110 kV Brazi West - S.C. TECNOSERVICE BUCURESTI S.A. Interconnection power substation
  • RK automation system for auxiliary service panels in the Ghizdaru, Gura Ialomitei and Domnesti Power Substations - National Company for Electricity Transmission "TRANSELECTRICA" S.A.
  • The integration of new 110kV substation bays afferent to the steam-gas combined cycle plant in the current 110kV Plant in COGENERATION PLANT BUCHAREST WEST - S.C. ELECTROCENTRALE BUCURESTI S.A. - ELECTROCENTRALE BUCHAREST Branch
  • Retrofitting the 110/20 kV Valcea North substation (SDFEE RM. VALNCEA) - S.C. ENERGOMONTAJ S.A. - IEA Bucharest Branch
  • Electricity metering system - outdoors of the plants on the 20KV side in the low power hydroelectric power plants of Hydroelectric power Unit Campina - S.C. ENERGOMONTAJ S.A. - IAE Bucharest Branch
  • Upgrading the 110 kV bay intended for the T52 Cogeneration Plant Paroseni transformer - S.C. ISPE S.A. (Institute for Studies and Power Engineering) Bucharest
  • Secondary compact substation. Power wiring in the generation halls, including the Safety control panel supplied from the Diesel generating set. Outdoor wiring (cable layouts, earthing, protection against atmospheric overvoltage) - S.C. UNICOM OSYS S.A.
  • Retrofitting of MV and LV power substations in SC OIL TERMINAL SA CONSTANTA - TS 123, TS 173, TS soda - lye Constanta bridge - S.C. ROMIB S.A.
  • Upgrading the 10kV Distribution System of S.C. OTELINOX S.A. Targoviste
  • Integration of the new 110kV substation bays afferent to the steam-gas combined cycle plant in the 110kV Substation in COGENERATION PLANT BUCHAREST WEST - S.C. ENERGOMONTAJ S.A. - IAE Bucharest Branch
  • Execution of a 6kV underground power line, for the supply of the auxiliary services in the 400/220/110kV interconnection power substation BRAZI VEST - S.C. TECNOSERVICE S.A.
  • Drafting technical documentation - Reorganization of the 6 and 0.4 kV Power Substations - S.C. TERMOELECTRICA S.A. - Electrocentrale Borzesti Branch
  • "Project on the capital repair and upgrade of the 6kV OB1S-OB2S substation and Upgrade of the OB1S-OB2S power substation for the supply of general services from the hydroelectric power units code CPV 74232310-0, 74232000-4" - S.C. COMPLEXUL ENERGETIC TURCENI
  • "Electric project on the integration of the 8MW cogeneration group in the 6kV SRA1-SRA3 electrical diagram" - CHIMCOMPLEX S.A. BORZESTI
  • Drawing up documentations on the Feasibility Study, the Technical Project, the Tender Book, Execution Details on the "Upgrading the Targu Jiu North substation" work - CN TRANSELECTRICA SA - ST CRAIOVA
  • Upgrading the auxiliary service MV and SUBSTATION bays in the Targoviste power substation - National Company for Electricity Transmission "Transelectrica" S.A. - Bucharest transmission branch
  • Drawing up the Execution Details documentation for the upgrade of the MV bay protections - S.C. IZOCONSTRUCT S.R.L. GALATI
  • "Upgrading the protections and the auxiliary systems of the 110kV/6kV T5 and T6 power transformers in SRA3 Petromidia" - SC ENEROPTIM SRL
  • "SC SPICUL SA electricity supply" - CHITILA, RUDENI Street - S.C. ENERGOMONTAJ S.A. - IEA Bucharest Branch

  • Wiring and automation systems, as well as technical support for the mounting and connection of a 0.4 kV Diesel generating set in the 0.4 kV power substation within the "STAR FOODS" Bucharest company - S.C. ROMIB S.A.
  • "Electricity supply of the Laminorul Sendzimir (ZM3) No. 3 site, of the BAL2 Cleaning and heating treatment line and of the TL2 Facing line, of the Finishing line (SL4), of the Assembly line (pk2) on 10kV and 0.4 kV in Otel Inox Targoviste." - S.C. OTELINOX S.A.
  • "Real time metering and monitoring system of electricity consumers in the 6kV substations; replacement of the metering and recording devices in the power control room in the 110kV substation". - S.C. UZINA TERMOELECTRICA MIDIA S.A.
  • "3-phase bus bar system for the supply of the ABB frequency converter cubicle afferent to the TESTING BENCH - GENERAL TURBO S.A." - S.C. GENERAL TURBO S.A.
  • TGD1 Distribution Control Panel for "STAR FOODS" SRL Bucharest - S.C. ROMIB S.A.
  • "Upgrading the secondary circuits and integration of the MILCOV, OLT COUNTY transformer substation in SCADA" - S.C. ENERGOMONTAJ S.A. - IEA Bucharest Branch
  • Upgrading the auxiliary service (20 kV) MV and substation bays in the Targoviste power substation - S.C. ENERGOMONTAJ S.A. - IEA Bucharest Branch
  • 110/20KV Traianu power substation, Teleorman County - S.C. ENERGOMONTAJ S.A. - IEA Bucharest Branch
  • 110/20/6kV Prefab substation and 20kV Breasta substation - S.C. ENERGOMONTAJ S.A. - IEA Bucharest Branch
  • 110/20kV Cernavoda substation - S.C. ENERGOMONTAJ S.A. - IEA Bucharest Branch
  • 110/20kV Potelu power substation, Olt County - S.C. ENERGOBIT SRL Cluj, Bucharest Branch
  • Designing the electricity metering system in the 220/110kV Isalnita substation - S.C. ENERGOBIT SRL Cluj, Bucharest Branch- Execution Details and AS BUILT design - Upgrading MV bays in the Tamadau 110/20/6kV transformer substation - S.C. ENERGOMONTAJ S.A - IEA Bucharest Branch
  • SCADA system for the 110/30 kV power station at Nucarilor Valley - S.C. ENERGOMONTAJ S.A. IEA Bucharest Branch
  • Design Documentation - Technical conditions for DASf and AAR plants inside of "Modernization MT cells (20kV) and transformer for internal services of 220/110/20kV power station Tg. Jiu Nord" - S.C. AUTOMATICA S.A.
  • DDE Design and As Built - Improving operating parameters of 20kV overhead line  connected to the 20kV power grid station to the Breasta county, by upgrading the neutral treatment - S.C. ENERGOMONTAJ S.A. IEA Bucharest Branch
  • DTAC, DTOE and BD Development for objective: Making power grids distribution for electricity supply in the area Ghitu - Molivisu, Arefu village, Arges - S.C. PROBIT S.R.L. Bucharest
  • Design of 33/110kV Pantelimon transformer substation  PT + CS phase (according to the design theme Annex 1 to the contract)
    Underground power line design of 110kV transformer substation connection to power grid substation - S.C. MONSSON ALMA S.R.L. Constanta
  • Creating designing documents of "Swich of 2 and 8 fans and exhausters '6kV cells' circuit breaker and protections" - S.C. ELECTRO-TOTAL S.R.L. Bucharest
  • Rehabilitation of 0.4kV electrical station's distribution block. Neutralization: PT, CS aquisition and installation, DE and installation, operating and maintenance instructions / Pram, execution technical asistance/ Instalation, starting up, As Built documentation. Turnkey project - S.C. SEMPRO S.R.L. Constanta

  • 110 kV power line cable from CEE Mereni to South Medgidia 400/110kV station. Technical documentation for Cernavoda – Constanta highway underpass.

  • 110 kV power line cable from CEE Mereni to South Medgidia 400/110kV station. Technical documentation for cable tray path construction autorisation. S.C. WestWind Mereni S.R.L

 
 
     